The “Yanergo” branch supplied electricity to a new residential complex in the Leninsky district

Electrical engineers from Yarenergo, a subsidiary of Rosseti Center PJSC, have completed work on connecting a residential complex on Karl Liebknecht Street in Yaroslavl to the power grid.

For the power supply of an apartment building, 6 kV cable lines with a length of 118 m were reconstructed, 800 m of 0.4 kV cable lines were built. The power source was a new transformer substation with two 630 kVA transformers.

The “Cascade” residential complex is a 10-story brick building consisting of five sections. A children’s playground will be set up on the adjacent territory, sports and recreation areas and guest parking lots will be provided.

“Technological connection is one of Yarenergo’s important activities. Timely connection of housing facilities, production, housing and communal services improves the quality of life of residents of Yaroslavl and provides opportunities for the development of the region,” the interim said. Deputy General Director – Director of the branch of PJSC “Rosseti Center” – “Yarenergo” Dmitry Litvinenko.

How Yaroslavl Oil Refinery Was Built. Milestones in history…

More

“invisible” link in the energy system of Russia

The Zagorsk pumped storage power plant was built on...

Bombing of Russian Belgorod… and raids on Ukrainian airports

"During the night the situation was turbulent," Gladkov...
Show your support if you like our work.

Author

Russia Desk
Russia Desk
The Eastern Herald’s Russia Desk validates the stories published under this byline. That includes editorials, news stories, letters to the editor, and multimedia features on easternherald.com.

Comments

Editor's Picks

Trending Stories