In Kaliningrad, work has begun to replace the pipeline on Batalnaya, Samarkandskaya and Ulyana Gromova streets.
Maxim Fedoseev, director of MP Kaliningradteploset, held an on-site meeting with the contractor and assessed the progress of the work. It is expected that the replacement of the pipeline section will eliminate the accident rate and increase the heat supply capacity. This is reported by the MP’s official telegram channel “Kaliningradteploset”.
From Wednesday April 13, excavations began on the site simultaneously on both sides of the site to be replaced. This, according to the contractor, will expedite the relocation of the networks and complete all installation work by mid-July.
After that, the workers will start improving the affected areas. According to the project, it will take another month and a half.