The Kirov mayor’s office explained how things are going with the company Gordormoststroy, which is preparing to repair the roads. The organization is gradually restocking its warehouses with the materials that will be needed during the season.
Road builders need sand, crushed stone and bitumen, for which storages are being built. About 50% of the material volume is already in stock. By the end of May, this figure will be increased to 100%, – reports the management of GDMS.
Weather permitting, repair work will begin in the middle of this month.
The company assured that the materials purchased are subject to strict laboratory control, their strength, composition and weight are checked. The materials go to the plant for the preparation of the asphalt only after verification.